Monday, April 2, 2012


Start of Building Pad


Delivering Screening


Another Septic Tank


Pad


Plumbing Rough


Plumbing Rough


Electrical T-Post


Footings



Footings



Footings



Footings



Footings



Friday, December 2, 2011

Soils Testing

Soils Mechanics Setting Up For Testing

Drilling



 
Drilling at 12'.  Hit water table at 6'
Would be more video but my phone rang and stopped recording.
Only took me three days to get this video posted.  It still is not posted correctly.  I like to post directly to blog and not through YouTube.  But for some reason it would not let me.  I will try to resolve.

Soils Mechanics should have soils test and foundation recommendation to me Monday afternoon or Tuesday morning.  Once we have that I can have post tension plans finished so plans can be submitted to City of El Paso for permit.  Will start pad as soon as we have report.

Tuesday, November 22, 2011

Demolition Continued

Still Coming Down

Had to resort to to a bobcat due to the mud

Almost all the way down


Stuck in the mud

Ruben says it will be done by Thanksgiving.
Soils testing to be completed 11/28/11

Friday, November 4, 2011

Flood and Demolition

First Setback ---- Flooding

Rio Ocotillo

Lake Driveway

Backyard

Start of Demolition - Problems with loader sinking in mud

Demolition